The shortage of storage space and high
rental rates force companies to build storage facilities independently.
However, such projects require very serious knowledge. Indeed, the main goal is
not just to build an object, but to "teach" it how to handle cargo
flows.
Therefore, the design phase is one of
the most important in the construction of the warehouse building design. With
description, we will begin a series of articles on this topic.
The design begins with the creation of
a design team. Its area of responsibility fully covers such blocks of work as:
1) logistic
calculation of a warehouse complex;
3) business
planning (feasibility study - feasibility study);
4) Construction
and equipment of the warehouse.
The above work, which is often called
subprojects, is fully initiated, executed and supervised by the project team.
But there are those that are not fully
within its competence — for example, the issue of project financing, marketing
research and staff selection.
In addition, it must be taken into
account that the work execution order is also of fundamental importance,
especially if the deadlines are very tight.
Finally, the third point that you need
to pay attention to is the formulation of the goal of creating the project.
Target designation should be unambiguous, measurable and achievable.
Roughly speaking, a warehouse for
storing our own products and a warehouse for the provision of logistics
services will be different. Having decided for yourself the question of
purpose, you need to answer the following two:
1. What
should be the characteristics of the warehouse complex?
2. How
can we understand that the goal has been achieved and the project has been
completed?
Examples of successfully formulated
project goals are presented in the corresponding box:
Examples of successful goal setting
for different warehouses
1. For the project of creating a distribution
centre
The main goal of the design work is
the design, construction, equipping and reaching the calculated indicators of
the company's distribution centre for commodity processing and storage of at
least 15 thousand items for the purpose of meeting the needs of the company's
sales divisions by reducing annual logistics costs for 4%.
2. For a commercial warehouse project
The main goal of the design work is
the design, construction, equipment and commercial launch of a pallet warehouse
with a total storage capacity of at least 10 thousand pallet places with an
average daily throughput of at least 800 pallet places and a discounted payback
period of no more than seven years (implied in the project documents the
concept of “pallet place” will be formalized by weight and size
characteristics).
Typically, a detailed designation of a
project is carried out directly by the project manager and agreed upon at the
level of top management or company shareholders.
Start of the project team
A thorough and complete formalization
of project indicators allows you to begin to form a project team. It begins the
analysis and generalization of marketing data in the context of the commercial
activities of the warehouse. The logistic examination of the land and the
analysis of goods flow to determine the main characteristics of the warehouse
complex, preliminary calculation of the investment indicators of the project.
The results of this phase of work are:
1. Justification
of the need for a warehouse complex.
2. The
study of options for the master plan.
3. Preliminary
calculation of the throughput and storage capacity of the warehouse (for each
option separately).
4. The
preliminary budget for the implementation of the project for each of the proposed
options. 5. Preliminary investment assessment of the project by options.
6. Conclusion
- a recommendation for choosing an option for the final (detailed) development.
How are results obtained?
Typically, the results obtained are
submitted for discussion to the company's management to decide on the
feasibility of further work and/or adjusting the goals and objectives of the
project.
If the results of the discussion are
positive, the project team proceeds to the detailed logistic design of the
warehouse complex and the preparation of the terms of reference (TOR) for
architectural and construction design of the facility. This stage completes the
logistics design with the following necessary results:
1. A
detailed master plan of the
site with traffic patterns of traffic and human flows.
2. The
geometric dimensions of the warehouse complex and its technological zoning.
3. Space-planning
decisions on the technological zones of the warehouse.
4. Calculation of requirements for
warehouse equipment (gates with dock leveller platforms, shelving equipment,
palletizers, scales, etc.).
5. Calculation
of needs for loading machinery and equipment (VET) (hydraulic trolleys,
forklifts, conveyors, reach trucks, high-rise commissioners, etc.).
6. Calculation
of requirements for warehouse personnel.
7. Description
of the main technologies for cargo handling.
8. Terms
of reference for architectural and construction design, indicating the
composition of the facilities of the warehouse complex (checkpoint, generator,
dining room, etc.) and all technological loads.
9. A
detailed budget for the implementation of the project.
10. Economic
calculation and determination of investment indicators of the project.
The second stage of work
At the next stage of work, the project
team holds tenders for the selection of organizations of the general designer
(architectural and construction design and approval of the project), the
general contractor (construction of the warehouse) and suppliers of warehouse
equipment and machinery. Based on the results of the tender, contracts are
concluded with the winners, and the project for creating a warehouse complex
goes into the stage of architectural and construction design. The simultaneous
selection of the general designer, general contractor and equipment suppliers
allows us to design the warehouse taking into account the technological base of
the general contractor and to provide all the requirements of the equipment
suppliers for the size of equipment installation sites, technological openings
and driveways. The result of this phase of the project are signed design
contracts, construction and supply of warehouse equipment. In parallel with the
architectural and construction design, the project team is engaged in a
detailed description of the warehouse operation technologies and selects a
warehouse management system (WMS), if necessary.
Typically, the duration of this stage
is several months, which allows the beginning of construction to fully detail
the technology, taking into account the functionality of the WMS solution. The
construction part of the project ends with the acceptance of the warehouse
complex by the State Commission with the signing of the relevant act. Now the
facility is ready for operation, and the project team is entering the most
difficult phase of the project - the withdrawal of the warehouse complex to the
calculated performance indicators. (This step will be discussed in more detail
in the next article in the series)
If the project's task is to create a
distribution centre in the interests of its own business, it is necessary to
conduct a prospective SWOT analysis of the company's activities without its own
retail centre and for the case of the project. In the economic part of the
project, the main attention should be paid to the issue of assessing and
reducing costs on a business scale. The relative predictability of sales allows
us to design unique technologies for processing goods flow, achieving the
required economic indicators for a given warehouse throughput. Just because of
the use of special technologies, the construction of such a retail centre will
be carried out according to a unique project.
This comment has been removed by the author.
ReplyDeleteWarehouse construction is the construction of a commercial warehouse in a pre-built or modular format designed for long term use. Warehouse construction projects often include high-rise office space, flexible production spaces, and multi-level facility support systems. Warehouse construction also includes the structural engineering services necessary to ensure that the warehouse meets all applicable codes and is safe enough for retaining walls operation. Warehouse construction jobs are a popular choice for companies involved in manufacturing and distribution because of the considerable capacity and storage of these types of buildings.
ReplyDeleteWhen a new building is needed to store and organize large volumes of goods, such as raw materials and finished goods, or when a current building is showing signs of wear, a warehouse conversion or a new construction project is the more preferred option. In addition to meeting specific business requirements, commercial warehouse construction jobs also allow the flexibility to meet local zoning requirements. Many states require businesses to have a minimum volume of space available for each type of business use. For instance, if a manufacturer produces goods that are used by a variety of retailers throughout the country, the manufacturer may wish to build a warehouse in either a northern or southern region depending on the availability of access roads, road access, and other factors.